File #: ID 24-4142    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 2/12/2024 In control: City Council
On agenda: 2/27/2024 Final action:
Title: Award Bid for the Airport Obstructions Light/Mark/Remove Existing Hydrants and Replace Project Construction Contract to Craig Plumbing Contractors, Inc. (Mike Wolfe)
Attachments: 1. Contractor Award Recommendation Memo-Craig Plumbing Contracotrs Inc, 2. HII Hydrant Award Recommendation_to City, 3. HII - Hydrant Bid Tabulation 02-07-2024, 4. E1S1V01C Lake Havasu City EXECUTED

COUNCIL COMMUNICATION

 

 

TO:                                          Honorable Mayor and Council

 

FROM:                     Mike Wolfe, P.E, Assistant City Engineer

 

 

SUBJECT:Title

Award Bid for the Airport Obstructions Light/Mark/Remove Existing Hydrants and Replace Project Construction Contract to Craig Plumbing Contractors, Inc. (Mike Wolfe)

 

FUNDING SOURCE:

90% Arizona Department of Transportation (ADOT) Grant Funding E1S1VO1C

10% Airport Fund (City match)

PURPOSE:

Award bid for the Construction Contract (500450) to Craig Plumbing Contractors, Inc., for Airport Obstructions Light/Mark/Remove Existing Hydrants and Replace Project BP24-PW-104007-500450 in accordance with City Code Sections 3.10.010.2 (A.R.S. Title 34) and 3.10.030.1.

 

BACKGROUND:

This project was part of an overall Airport Operations Safety Improvement for removal of obstructions. In this case above ground hydrants were a collision safety concern. A project grant through the ADOT Multimodal Planning Division was awarded and accepted on April 27, 2021, for 90% construction grant funding and 10% construction local match. Total Estimated Project including Design, Construction and Construction Engineering is $450,000 with a $45,000 local match. On February 7, 2024, sealed bids were opened and publicly read for the project and three (3) bids were received in response.

 

Combs Construction Company Inc. (Glendale, AZ) -                      Base Bid + Allowance $577,050

Technology Construction Inc. (Prescott, AZ) -                                 Base Bid + Allowance $348,000

 

The responsive low bidder is:

Craig Plumbing Contractors, Inc. (Lake Havasu City, AZ) -  Base Bid + Allowance $292,960.03

 

COMMUNITY IMPACT:

This project will provide enhanced Airport Safety.

 

FISCAL IMPACT:

Funding in the amount of $292,960.03 is available as ADOT 90% Grant of $263,664.03 and City match from the Airport Fund of 10% in the amount of $29,296.

 

ATTACHMENTS:

Bid Recommendation

C&S Award Recommendation

Bid Tabulation

Lake Havasu City Executed Grant E1S1VO1C

 

SUGGESTED MOTION: Recommended Action

I move to award the bid for the Airport Obstructions Light/Mark/Remove Existing Hydrants and Replace Project Construction Contract to Craig Plumbing Contractors, Inc., in the amount of $292,960.03.