File #: ID 18-1641    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 5/8/2018 In control: City Council
On agenda: 5/22/2018 Final action:
Title: Adopt Resolution No. 18-3227 Approving the Submission of a WaterSMART Grant Application to the Bureau of Reclamation for the Infrastructure Design from the Recovery Well to the Effluent Pipeline (Doyle Wilson)
Attachments: 1. Resolution No. 18-3227, 2. Map - Project Location
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

COUNCIL COMMUNICATION

 

 

 

TO:                                          Honorable Mayor and Council

 

FROM:                     Doyle Wilson, Water Resources Coordinator

 

 

SUBJECT:Title

Adopt Resolution No. 18-3227 Approving the Submission of a WaterSMART Grant Application to the Bureau of Reclamation for the Infrastructure Design from the Recovery Well to the Effluent Pipeline (Doyle Wilson)

Body

 

FUNDING SOURCE:

Bureau of Reclamation WaterSmart Water Conservation Field Services Grant

Irrigation and Drainage District Fund

 

PURPOSE:

Establish engineering design work for construction of infrastructure from the North Regional recharge field recovery well to North Regional effluent pipeline.

 

BACKGROUND: 

A water well was constructed in 2016 at the North Regional Wastewater Treatment Plant (WWTP) recharge field for the purpose of recovering recharged effluent.  Water from this well is planned to be delivered, as necessary, to the City’s main effluent pipeline installed nearby when the North Regional WTTP was constructed in 2007. Creation of engineering design of the necessary infrastructure and appurtenances to successfully pump and deliver water from the well to the effluent pipeline is the first step of the process.

 

COMMUNITY IMPACT:

This project represents the initial stage to increase the availability of treated wastewater for reuse that would replace potable water irrigation and lengthen availability of the City’s Colorado River allocation.

 

FISCAL IMPACT:

The Field Services grant opportunity is a 50/50 percent cost share venture, that includes appropriate in-kind service by City staff. Engineering estimate on the design work is $25,000. Net Fiscal Year 2018-19 impact after reimbursement will be $10,287.00 or less with in-kind service included.

 

ATTACHMENTS:

Resolution No. 18-3227

Map - Project Location

 

SUGGESTED MOTION:Recommended ACtion

I move to approve Resolution No. 18-3227 approving the submission of a WaterSMART Grant application and authorizing the City Manager to execute documents and implement the activities funded and required by the grant.