Title: Discussion and Action: Bid for the 2025 Water Main Replacement Project to Mountain High Excavating, LLC (Brent Cummings)
Attachments: 1. Bid Tabulation, 2. Letter of Recommendation

COUNCIL COMMUNICATION

 

 

TO:                                          Honorable Mayor and Council

 

FROM:                     Brent Cummings, Project Manger

 

 

SUBJECT:Title

Discussion and Action: Bid for the 2025 Water Main Replacement Project to Mountain High Excavating, LLC (Brent Cummings)

Body

 

FUNDING SOURCE:

Capital Improvement Plan (CIP) - Water Funds

PURPOSE:

To consider the award of the base bid and four (4) additive alternates contract (500678) for the 2025 Water Main Replacement Project in accordance with City Code §§ 3.10.010.2 (A.R.S. Title 34) and 3.10.030.1.

 

BACKGROUND:

After careful evaluation of the water system, the City’s Water Division along with Capital Programs identified the following roads needing to be replaced: Acoma Boulevard, Wood Lane, Southwind Place, Southwind Avenue, Inca Lane, Scout Drive and Indian Pipe Lane. This project has four (4) additive alternatives as follows: Alternative 1- Serenidad Vereda and Plaza Del Sol, Alternative 2- Rango Place, Alternative 3- Rango Court, and Alternative 4- Pony Lane and Pony Place. The City contracted with Kimley-Horn Engineering to develop replacement plans for these water system sections as well as help advertise for construction.

 

On August 6, 2025, sealed bids were opened for the project and four bids were received in response:

 

Mountain High Excavating - Base Bid plus four additive alternates = $3,575,694

Pat Bern- Base Bid plus four additive alternates                                = $4,624,033

Pronghorn Services - Base Bid plus four additive alternates             = $5,096,599

Standard Construction - Base Bid plus four additive alternates        = $5,961,735

 

COMMUNITY IMPACT:

The replacement of the existing water mains, water services and fire hydrants will enhance the neighborhood also providing reliable potable water. Upgrading new water mains, water services, new fire hydrants and water delivery to the community now and into the future will be beneficial to the residents of Lake Havasu City.

 

FISCAL IMPACT:

Funds in the amount of $4,740,000 are allotted and available in the Fiscal Year 2025-26 Capital Improvement Program utilizing Water funds. This amount included design and construction management.

 

ATTACHMENTS:

Bid Tabulation

Letter of Recommendation

 

SUGGESTED MOTION:Recommended Action

I move to award the base bid and four additive alternates for 2025 Water Main Replacement Project to Mountain High Excavating in the amount of $3,575,694.