Title: Discussion and Action: Construction Contract to Perco Rock Company for the Havasupai Wash 6 Project (Shawn Clarke)
Attachments: 1. Bid Tab, 2. Bid Recommendation

COUNCIL COMMUNICATION

 

 

 

TO:                                          Honorable Mayor and Council

 

FROM:                     Shawn M. Clarke, Civil Engineer

 

 

SUBJECT:Title

Discussion and Action: Construction Contract to Perco Rock Company for the Havasupai Wash 6 Project (Shawn Clarke)

Body

 

FUNDING SOURCE:

CIP - Flood Control Fund

 

PURPOSE:

To consider a Construction Contract 500409 with Perco Rock Company for the Havasupai Wash 6 in accordance with City Code §§ 3.10.010.2 (A.R.S. Title 34) and 3.10.030.1.

 

BACKGROUND:

As part of the Wash Stabilization Program, the City commissioned a two-part study to evaluate, prioritize and recommend improvements for the system of washes within the City boundaries. Havasupai Wash 6, located between Sandwood Drive and Bombay Drive, is listed as the sixth worst reach in our City limits.

 

The City selected Kimley Horn and Associates to prepare the plans and specifications for the proposed project.

 

On September 4, 2024, eight (8) bids were received. 

 

The lowest responsive, responsible bidder is:

 

Perco Rock Company                                          

Base Bid plus Force Account:  $685,109  

Base Bid plus Additive Alternate plus Force Account: $936,389

 

COMMUNITY IMPACT:

This project will provide drainage improvements and slope stabilization measures to an important wash in our city.

 

FISCAL IMPACT:

Flood Control Fund Funds are allocated and available in the Fiscal Year 2024-25 Capital Improvement Plan in the amount of $2,000,000.

 

ATTACHMENTS:

Bid Tab

Bid Recommendation

 

SUGGESTED MOTION:RecoAction

I move to award the base bid plus additive alternate plus force account for the Havasupai Wash 6 Project to Perco Rock Company in the amount of $936,389.